EnviScan In-Situ Contaminant Monitoring - CASE STUDIES

CASE STUDY 1: Contamination Monitoring at Gas Station

Survey objective
To monitor a contamination situation at a small gas station at which the source of the contamination has been removed. The location has been mapped just before removing the source and 1 year after the source had been removed.

Fieldwork
During fieldwork a 6 feet x 6 feet grid was outlined. Experience shows that this is the optimum choice for a grid to detect small 'spots' of contamination if present. After establishing the local grid, a radar survey with 200 MHz antenna (approx. 20 feet deep) Normally a location with the size of on average gas station can be measured within half a day's fieldwork. The data processing and preparation of a report takes a few days.

Results
The field data are converted into a 3-dimensional model using EnviScan software. In this model the relative contamination levels are visualized in different colors. If the relative contaminant levels of the model are calibrated with results of a limited number of actual analytical data obtained from available boring data, the relative contaminant levels can be converted to 'absolute' contaminant levels.

Comparison of survey data from 1997 and 1998 (see figure) shows the difference in contaminant levels at this site between 1997 and 1998.

 

CASE STUDY 2: Contaminant Survey and Monitoring of Natural Attenuation on an Airfield in Asia

Survey Objective
The purpose of the first survey performed in 1999 was to determine the extent of the soil contamination present under three feet thick concrete runway. Conventional borehole drilling combined with laboratory analysis did not produce sufficient information to determine the extent of the subsurface soil contamination. This was mainly due to large area involved and limited access for collection of samples underneath the concrete.

A second survey was performed in 2001 survey was to verify the efficiency of the in-situ remediation through natural attenuation.

Fieldwork
For this large site, a 30 feet x 30 feet grid was outlined. The measurements were carried out with a 200 MHz antenna pulled behind a vehicle. The computer and peripherals were placed inside the vehicle. The fieldwork took approximately one week using GPS for positioning during the survey.
 

Results
The radar data were converted on location with an adapted version of our EnviScan software in order to process the large quantity of data. The obtained relative contamination values were converted with the aid of limited analytical data into absolute values and classified in two categories: light contamination (mineral oil <1000 mg/l) and heavy contamination (mineral oil >1000 mg/l). In comparing the two surveys, it was shown that contamination was removed only slowly through natural attenuation.  Based on the results of the second radar survey a new remediation plan was set up, in which selected heavily contaminated soils were excavated and the light contaminated soil were treated using in-situ bioremediation.

Repeated (yearly) surveys can be performed to monitor progress and effectiveness of the remediation. The results of each survey can be used to optimize remediation efforts, and consequently reduce total operating time and remediation costs.

BACK

Geophysical Services - HOME

 

   Fieldwork  

3D results  

 Monitoring contamination  

Parallel radartracks in 1999   Results 1999